stone/sculpture lifting equipment

Stone Conversations : Archive 3 : Message 00140

From: "John VanCamp" <jvcstnwrks@xxxxxxxxxxxxx>
Date: Mon, 9 Sep 2002 23:17:03 -0500
Subject: stone/sculpture lifting equipment

Quoted text begins.-- Original Message --
End of quote.

From: "Clive Murray-White" <clivemw@xxxxxxxxxxxxxxx>
To: <stone@xxxxxxxxxxxxx>
Sent: Monday, September 09, 2002 9:42 PM
Subject: stone/sculpture lifting equipment

Quoted text begins.Thanks John,
End of quote.


Quoted text begins.Any chance that you know the answers to my questions sent to
End of quote.

Simon?

Clive. In my old shop I used a two section high tubular
scaffolding with a piece of 4 inch steel square tube across the
upper frames and a 2 ton chain hoist hanging from the square
tube. Largest stone I lifted with that rig was around 4800 lbs.
Didn't try to roll it with that load. We once lifted a 6000 lb
+ mantle and rolled it into place by using two sections of
scaffolding side by side with two chain hoists, and it went like
clock work. Did spend about 3 days preparing every thing for
the lift, so that there wouldn't be any surprises once we got
the stone in the air. If you can find a 4 or 5 inch I beam, and
a rolling block that will fit it, you can probably do this
without any problem. However, you might want to look into
getting an all terrain forklift and operator for a few hours,
and avoid the what ifs. I only build scaffolding rigs in places
where we can't get a piece of equipment, or the clients budget
won't allow it. Good luck and let us all know how it works out.
John VanCamp

End of main content.
Begin local navigation menu:
End of local navigation menu.

©1998-2006 About Stone. Designed, maintained and hosted by Diversity Studio.

Mail converted by MHonArc 2.6.16 08 July 2006